When quotations for custom heat-resistant castings differ, first check whether the suppliers priced the same requirement. The comparison should cover the drawing revision, alloy, quantity, finished condition, inspection and delivery scope. Price becomes more informative after these differences are visible.
Use a comparison sheet that preserves the bidder’s stated offer. Do not replace an exclusion with an assumption that the work will be included later.
Normalize the technical requirement
Send the same controlled package to each bidder. Where a supplier proposes a different alloy, section, weight or manufacturing approach, ask for it as a separately identified alternative. Keep the price for the requested specification visible.
Heat resistance includes environmental resistance and mechanical behavior at temperature. A material comparison therefore needs the relevant service conditions; a grade name or quoted temperature alone cannot establish equivalent performance.[S2]
A lower-priced alternative may deserve engineering review. It should not enter the main comparison as if it were already approved.

Compare included work line by line
| Quotation line | Question to resolve |
|---|---|
| Drawing and material | Is the same revision, grade and delivery condition quoted? |
| Quantity and weight basis | Is the price per piece, per set or by weight? Is the quoted weight estimated or measured? |
| Tooling | Is there a separate charge? What scope, maintenance and future use are covered? |
| Finished condition | Are machining, joining, mesh, accessories and finishing included where required? |
| Inspection | Which checks, reports and third-party services are included or separately charged? |
| Delivery | What packaging, named delivery point, freight and commercial terms apply? |
The Foseco handbook identifies additional testing as a cost that should be agreed between buyer and supplier before ordering. A quotation with extra inspection is not directly comparable to one that excludes those checks.[S7]
Put one-time and recurring costs in different rows
Keep tooling, first-part work and recurring piece prices separate. Show sample quantity and batch quantity explicitly. Ask whether a later repeat order uses the same commercial basis or requires a new quotation.
Pattern design and selection consider production quantity, production cost, manufacturing time and tooling use. This supports asking how the tooling proposal fits the expected order pattern. It does not establish the actual tooling cost for your part.[S5]

Close the gaps before selecting the offer
Add four response categories to the sheet: included, excluded, separately priced and pending clarification. Assign each open item an owner. Compare the offers again after the material and supply-scope differences have been resolved.
Keep purchase price separate from any forecast of operating cost. A longer service life, reduced downtime or energy saving needs relevant evidence and a consistent calculation basis. Do not add an assumed saving to make an otherwise incomplete quotation appear preferable.
For a comparable ECOOSUN quotation, send the approved drawing, material requirement, quantity and required inspection scope. Include your delivery location and identify any tooling, machining or accessories that should be priced separately.
Related product information: Heat Treatment Baskets · Heat Treatment Trays · Send drawings and requirements to ECOOSUN.
Technical references and scope
The references support the marked technical principles. The purchasing checklists and workflow are editorial applications. Historical references do not establish current standard editions, project-specific acceptance limits or ECOOSUN performance guarantees.
- S2. Foundry Handbook, Volume 2: Cast Steel (Chinese-language reference; title translated); PDF pages 188, 189, printed pages 171, 172. Heat resistance includes environmental/oxidation resistance and high-temperature mechanical behavior, including time-dependent behavior.
- S5. Foundry Tooling Design Handbook (Chinese-language reference; title translated); PDF pages 9, printed pages 7. Tooling selection considers production and technical requirements; pattern dimensions include process allowances and contraction.
- S7. Foseco Ferrous Foundryman's Handbook; PDF pages 130, 131, printed pages 119, 120. Inspection scope is specified; additional testing has cost implications to agree before ordering.
Related RFQ and Supplier Evaluation Resources
Prepare the drawing, operating conditions and acceptance requirements before comparing quotations or selecting a casting supplier.
- How ECOOSUN Reviews Drawings, Samples and Operating Conditions Before Quotation
- Heat Treatment Furnace Parts RFQ Checklist: What Buyers Should Send a Manufacturer
- How to Evaluate a Heat-Resistant Furnace Parts Supplier
- How to Prepare a Worn-Sample Replacement Package for Furnace Parts
Product families where this guidance may apply
Manufacturing and quality evidence · Official company facts and current catalog
Information for a Faster Quotation
Provide the drawing revision, product family, dimensions, furnace conditions, quantity and required inspection documents. Final design, material and acceptance criteria require project-specific agreement.
Request a Custom Quote · Send Your Drawing · WhatsApp ECOOSUN